Skip to content
Search Take the survey

↑ ↓ choose a page. Enter searches everything, with exact title matches first; kind:source and other filters work there. Esc closes.

← wiki/sources
source

Energy Commission backup generating project San Jose Data Center 04 (web)

Online ↗

Type
source
Created
2026-11-22
Updated
2026-11-22
Sources
1
Tags
A, data-centers, energy, backup-generation, california, permitting, san-jose, pge, microsoft
Elements
A
Origin
web
Tier
primary
Citable
yes
Url
https://www.energy.ca.gov/powerplant/backup-generating-system/san-jose-data-center-04
Rehost
yes

Links to 13, referenced by 15

Energy Commission backup generating project San Jose Data Center 04 (web)

Citation

California Energy Commission (CEC). “San José Data Center 04.” Project page of the Power Plant Listing, technology “Backup Generating System”. Web page, no date. https://www.energy.ca.gov/powerplant/backup-generating-system/san-jose-data-center-04. Fetched 2026-11-22; read 2026-11-22. Copy: raw/web/2026-11-22 Energy Commission backup generating project San Jose Data Center 04.md (original: raw/web/2026-11-22 Energy Commission backup generating project San Jose Data Center 04.html).

Bottom line

  • The CEC project page for San José Data Center 04 (SJDC 04), a Microsoft data center campus. Its maximum electrical demand is 97.8 megawatts (MW). Its status is “Under Review”.
  • The campus has two four-story data center buildings and Tier 4 diesel backup generators. PG&E is the local utility.

Background

The CEC is a California state agency. This page is one of the 12 project pages that the Energy Commission power plant listing backup generating systems (web) links. Microsoft Corporation is the project owner. The docket number is 22-SPPE-02, the capacity is 97.8 MW and the location is San José, California. The project status is “Under Review” and the project type is “Small Power Plant Exemption”.

Key claims

  • “This proceeding is for the potential exemption of a data center project in the City of San José , California.” (page text)
  • “The project would include two four-story data center buildings, each approximately 315,639 gross square feet” (Project Description)
  • “The total maximum electrical demand of the project would be 97.8 megawatts (MW).” (Project Description)
  • “The Tier 4 diesel backup generating facilities with selective catalytic reduction and diesel particulate filters would consist of thirty-two 3 MW primary emergency generators, two 0.5 MW administrative emergency generators, and two 0.8 MW storage tank area emergency generators.” (Project Description)
  • “The sole purpose of the backup generating facilities is to provide electrical power to support the data center campus operations in the event of loss of electrical service from the local electric utility provider, Pacific Gas and Electric Company.” (Project Description)
  • “The Small Power Plant Exemption (SPPE) process allows applicants with facilities between 50 and 100 MW to obtain an exemption from CEC’s jurisdiction and proceed with local permitting rather than requiring CEC certification.” (Small Power Plant Exemption)

Evidence and method

A project page from a state agency’s website. It gives the docket’s fields, a project description and, for some projects, key dates with links to docket documents. This library does not hold the docket documents.

Limits

  • The docket number is from 2022, and the status is still “Under Review”. The page gives no key dates and does not say why.
  • The listing spells the name “San José Data Center 04”. The row’s title spells it “San Jose”.
  • The project description is the applicant’s proposal, in the conditional. The page can change after the fetch date.

Suggest a change to this page

Source file: wiki/sources/Energy Commission backup generating project San Jose Data Center 04 (web).md, updated 2026-11-22.

Suggest or correct

Know a report, dataset or law that belongs here? Found something wrong? Have a question the sources could answer? A consortium member reads every suggestion and decides. Nothing changes until a person makes the change, and the Suggestions page shows what happened to it.

About you (optional)

Your name and email stay with the team; we use the email only to reply. Your institution may appear on the contributors board.